sort by date sort by cost
Total 10 entries found , Cost: 364.7 million FCFA
Mar 05, 2024 CAMWATER SIGNE 41.5 million FCFA 0012/M/CAMWATER/DG/DAJM/CIPM/2024
RECRUTEMENT D`UNE MAITRISE D`OEUVRE CHARGEE DU CONTROLE DES TRAVAUX DE LA REHABILITATION/CONSTRUCTION DE LA RESIDENCE DU DG CAMWATER
Prestataire: ETS LE BARON MULTIPLE
2023 C_ESEKA ATTRIBUE
Réhabilitation des CSI de Nguibassal 2 et Song Badjeck
Prestataire: ETS LE BARON MULTIPLE
2023 C_ESEKA ATTRIBUE
TRAVAUX DE TRAITEMENT DES POINTS CRITIQUES DE LA ROUTE COMMUNALE LIKABO-MAYENBOCK (3KM)
Prestataire: ETS LE BARON MULTIPLE
2023 C_ESEKA ATTRIBUE
TRAVAUX DE RÉHABILITATION DE CERTAINS CSI (SONG BADJECK) LOT 2
Prestataire: ETS LE BARON MULTIPLE
2021 C_MBANKOMO ATTRIBUE
Construction d`un bloc de deux(02) salles de classe à l`Ecole Publique de Mbankomo
Prestataire: ETS LE BARON MULTIPLE
Oct 05, 2020 C_MESSONDO SIGNE 16.3 million FCFA 02/LC/RCE/DNK/CMDO/2020
Construction d`un bloc maternel à l`Ecole Maternel de DJASSOCK, arrondissement de MESSONDO, département du NYONG et KELLE
Prestataire: ETS LE BARON MULTIPLE
Oct 05, 2020 C_MESSONDO SIGNE 34.8 million FCFA 004/LC/RCE/DNK/CMDO/2020
Achèvement des travaux de construction du CSI de BIDJOCKA, arrondissement de MESSONDO, département du NYONG et KELLE
Prestataire: ETS LE BARON MULTIPLE
Jul 17, 2020 C_YAOUNDE_I RECEPTIONNE 16.5 million FCFA 006/M/CAY1ER/SMP/2020
EP d`Olembe: construction d`un bloc de deux salles classe
Prestataire: ETS LE BARON MULTIPLE
Jun 19, 2020 MINFOPRA SIGNE 245.1 million FCFA 06/M/MINFOPRA/CIPM/2020
Construction d`un bâtiment R+1 pour la salle de conférence et d`un restaurant au MINFOPRA
Prestataire: ETS LE BARON MULTIPLE
Sep 11, 2019 MINFOPRA SIGNE 10.5 million FCFA S2/44/016/LC/MINFOPRA/CIPM/2019
Construction d’un hangar pour l’accueil et la réception des usagers
Prestataire: ETS LE BARON MULTIPLE