Jul 18, 2022
C_NGAOUNDAL
RECEPTIONNE
16.9 million
FCFA
10/LC/MO/CIPM/CNDAL/2022
LES TRAVAUX DE CONSTRUCTION D`UN BLOC DE DEUX LOGEMENTS D`ASTREINTE POUR ENSEIGNANTS A L`ECOLE PUBLIQUE DE KASSA.
Jun 16, 2022
C_TIBATI
SIGNE
45.0 million
FCFA
009/LC/MO/CIPM/C-TIB/2022
Finition de 12 boutiques au centre commercial
Jan 28, 2022
C_BANYO
SIGNE
38.8 million
FCFA
04/LC/C-BYO/SG/STADU/CIPMP/2022
TRAVAUX DE CONSTRUCTION DE DEUX (02) PARCS D`INTERVENTION ZOO SANITAIRE ÉQUIPÉS D`UN BLOC LATRINES A 02 CELLULES DANS LES LOCALITÉS DE NGANNI ET NYAMSOURE
Jan 28, 2022
C_BANYO
SIGNE
21.5 million
FCFA
02/LC/C-BYO/SG/STADU/CIPMP/2021
TRAVAUX DE MATÉRIALISATION DES PISTES A BÉTAIL, MBAH-MBAMTI MAGORO - MBAMTI KATARKO (40km)
Apr 20, 2021
C_TIBATI
RECEPTIONNE
18.8 million
FCFA
011/LC/MO/CIPM/C-TIB/2021
TRAVAUX DE MATERIALISATION DE PISTES A BETAIL NGATT - TIBATI (35KM) DANS LA COMMUNE DE TIBATI