Total 3 entries found , Cost: 192.0 million FCFA
May 31, 2017 DR_MINATD_NW SIGNE 12.0 million FCFA 30/JO/RDMINMAP/NWRTB/2017
Control and supervision of the construction works of the Residence of the Governor of the NWR (Phase II)
Prestataire: LOUMINOUS GROUP FOR APTITUDE MISSING
May 30, 2017 DR_MINATD_NW SIGNE 150.0 million FCFA 29/C/MINMAP/RDNW/2017
Construction works of the Residence of the Governor of the NWR (Phase II)
Prestataire: ETS ANUTEMEH JOHNSON FRU MULTIPLE
Mar 29, 2017 DR_MINATD_NW RECEPTIONNE 30.0 million FCFA 08/JO/RDMINMAP/NWRTB/2017
Construction of the residence of the Divisional Officer in Santa (phase II)
Prestataire: NGWATRA ENTERPRISE LTD INACTIF