Total 16 entries found , Cost: 269.6 million FCFA
2018 C_MOZOGO ATTRIBUE
CONSTRUCTION D`UN BLOC DE DEUX SALLES DE CLASSES EQUIPEES ET D`UN BLOC DE LATRINES A TROIS COMPARTIMENT AU CETIC DE OUZAL (LOT 1)
2018 C_MOZOGO INFRUCTUEUX
TRAVAUX DE CONSTRUCTION D`UN BLOC DE DEUX SALLES DE CLASSE AVEC LATRINES A L`EP DE MANDOUSSA-DZA ET A L`EP DE HITERE CHACUNE (LOT 02)
Prestataire: MISSING
2018 C_MOZOGO INFRUCTUEUX
CONSTRUCTION D`UN FORAGE PRODUCTIF EQUIPE DE POMPE A MOTRICITE HUMAIN A MOZOGO-KAMDJIDJI DANS LA COMMUNE DE MOZOGO
Prestataire: MISSING
2018 C_MOZOGO INFRUCTUEUX
Construction d`un bloc de 2 salles de classe au CETIC D`OUZAL (RP)
Prestataire: MISSING
2018 C_MOZOGO INFRUCTUEUX
CONSTRUCTION D`UN BLOC DE DEUX (02) SALLES DE CLASSE EQUIPEES A L`ECOLE PUBLIQUE DE DOUVAL VARA DANS LA COMMUNE DE MOZOGO, ARRONDISSEMENT DE MAYO-MOSKOTA
Prestataire: MISSING
2018 C_MOZOGO INFRUCTUEUX
TRAVAUX D`EXTENSION DU RESEAU ELECTRIQUE A MOZOGO (QUARTIER TALLATAKAZAR ET LA REHBILITATION DU RESEAU ELECTRIQUE DE MOSKOTA, DANS L`ARRONDISSEMENT DE MAYO-MOSKOTA
Prestataire: MISSING
Nov 12, 2018 C_MOZOGO SIGNE 8.0 million FCFA 011/LC/C-MOZ/CIPM/AI/2018
CONSTRUCTION D`UN FORAGE PRODUCTIF EQUIPE DE POMPE A MOTRICITE HUMAIN A MOZOGO-KAMDJIDJI DANS LA COMMUNE DE MOZOGO
Prestataire: PRAM'S GOLDEN MISSING
Nov 09, 2018 C_MOZOGO SIGNE 18.0 million FCFA 010/LC/C-MOZ/CIPM-TBEC/2018
Construction d`un bloc de 2 salles de classe au CETIC D`OUZAL (RP)
Prestataire: ETS LE PROGRES PLUS MULTIPLE
Oct 15, 2018 C_MOZOGO SIGNE 42.7 million FCFA 007/LC/C-MOZ/CIPM/TBEC/2018
CONSTRUCTION D`UN BLOC DE DEUX SALLES DE CLASSES EQUIPEES A L`EP DE KORSAMBA ET A L`EP DE KARAZAWA (LOT N°2),
Prestataire: ETS LE PROGRES PLUS MULTIPLE
Oct 12, 2018 C_MOZOGO SIGNE 16.0 million FCFA 005/LC/C-MOZ/CIPM/TBEC/2018
Construction d`une Tribune Officielle et la réhabilitation du complexe sportif à Mozogo dans l`Arrondissement de MAYO-MOSKOTA(RP)
Prestataire: ETS ABBA MAHAMA ET FILS INACTIF
Sep 24, 2018 C_MOZOGO SIGNE 48.6 million FCFA 008/LC/C-MOZ/CIPM-TBEC/2018
CONSTRUCTION D`UN BLOC MATERNEL EQUIPE A L`ECOLE MATERNELLE DE MOSKOTA ET CONSTRUCTION D`UNE CLÔTURE A L`ECOLE MATERNELLE DE MOZOGO (LOT N°3)
Prestataire: ETS LA JOIE MULTIPLE
Sep 24, 2018 C_MOZOGO SIGNE 17.4 million FCFA 009/LC/C-MOZ/CIPM/AI/2018
CONSTRUCTION D`UN FORAGE PRODUCTIF ÉQUIPÉ DE POMPE A MOTRICITÉ HUMAINE A L`ECOLE MATERNELLE DE MOSKOTA ET A L`EP DE GOKORO DANS LA COMMUNE DE MOZOGO
Prestataire: PRAM'S GOLDEN MISSING
Aug 17, 2018 C_MOZOGO SIGNE 10.0 million FCFA 003/LC/REN/DDMT/C-MOZ/SG/ST/2017
TRAVAUX D’ÉCLAIRAGE PUBLIC PAR ÉNERGIE SOLAIRE (08 LAMPADAIRES) DANS LE CENTRE URBAIN DE MOZOGO
Prestataire: ETS MOUSSA BIZGO ET COMPAGNY MISSING
Jul 27, 2018 C_MOZOGO SIGNE 45.0 million FCFA 002/LC/C-MOZ/CIPM/TBEC/2018
TRAVAUX DE CONSTRUCTION D`UN BLOC DE DEUX SALLES DE CLASSE AVEC LATRINES A L`EP DE MOUDOUKOA ET A UEP DE OUPAI-KIRBI CHACUNE (LOT 1)
Prestataire: ETS LE PROGRES PLUS MULTIPLE
Jul 27, 2018 C_MOZOGO SIGNE 45.0 million FCFA 001/LC/REN/DDMT/C-MOZ/SG/ST/2018
TRAVAUX DE CONSTRUCTION D`UN BLOC DE DEUX SALLES DE CLASSE AVEC LATRINES A L`EP DE MANDOUSSA-DZA ET A L`EP DE HITERE CHACUNE (LOT 02)
Prestataire: ETS LE PROGRES PLUS MULTIPLE
Oct 24, 2017 C_MOZOGO RECEPTIONNE 19.0 million FCFA 001/LC/C-MOZ/CIPM/TBEC/2017
CONSTRUCTION D`UN BLOC DE DEUX (02) SALLES DE CLASSE A L`EP DE ZENEME, ARRONDISSEMENT DE MAYO-MOSKOTA
Prestataire: ETS LE PROGRES PLUS MULTIPLE