Sep 23, 2022
C_EDEA_II
RECEPTIONNE
21.6 million
FCFA
LC n°008/LC/CAED 2/SG/SAPM/2022
Equipement de trois (03) CSI (MALIMBA FARM, MALIMBA Urbain, MALIMBA Gare)
Sep 09, 2022
C_EDEA_II
SIGNE
9.7 million
FCFA
LC n°001/LC/CAED 2/SG/SAPM/2022
MAITRISE D`OEUVRE DES TRAVAUX D`ENTRETIEN DE LA ROUTE : EKITE-POUT-NKAK-NDEMBE Y COMPRIS LA CONSTRUCTION DE 02 DALOTS (3,70 km )
Sep 08, 2022
C_EDEA_II
SIGNE
196.7 million
FCFA
Mn°001/M/CAED 2/SG/SAPM/2022
EXECUTION DES TRAVAUX D`ENTRETIEN DE LA ROUTE EKITE-POUT-NKAK-NDEMDE Y COMPRIS LA CONSTRUCTION DE 02 DALOTS ( 3,70 km )
Aug 25, 2022
C_EDEA_II
RECEPTIONNE
8.0 million
FCFA
LC n°004/LC/CAED 2/SG/SAPM/2022
Construction d’un Forage au CSI de NGONGA
Aug 12, 2022
C_EDEA_II
SIGNE
7.5 million
FCFA
LC n°006/LC/CAED 2/SG/SAPM/2022
Equipement du Bloc Maternité du CSI de MALIMBA FARM
Aug 09, 2022
C_EDEA_II
SIGNE
51.0 million
FCFA
Mn°003/M/CAED 2/SG/SAPM/2022
TRAVAUX D`ELECTRIFICATION DU VILLAGE POUTLOLOMA EN ENERGIE SOLAIRE DANS LA CAED 2
Aug 02, 2022
C_EDEA_II
RECEPTIONNE
24.8 million
FCFA
LC n°005/LC/CAED 2/SG/SAPM/2022
Réhabilitation des routes communales tronçon entrée Ekite 3-Dernière maison (800km) Malimba urbain (2km) Malimba gare (1km) Entrée cité des cadres-aison blanche (300m) Ekite 3-Rose croix (300m)
Jul 22, 2022
C_EDEA_II
RECEPTIONNE
18.9 million
FCFA
LC n°002/LMC/CAED 2/SG/SAPM/2022
Construction d`un bloc de deux salles de classe à l`école publique de Ekite Pilote Groupe 1 : Lot 1
Jul 22, 2022
C_EDEA_II
SIGNE
28.7 million
FCFA
LC n°007/LC/CAED 2/SG/SAPM/2022
Extension de la ligne élecrique Poutloloma 1 - Poutloloma 2
Jul 22, 2022
C_EDEA_II
SIGNE
68.9 million
FCFA
Mn°002/M/CAED 2/SG/SAPM/2022
Construction d`un cercle municipal à Edea II
Jul 15, 2022
C_EDEA_II
RECEPTIONNE
24.8 million
FCFA
LC n°003/LC/CAED 2/SG/SAPM/2022
Construction d`un bloc maternel à GEPS Ekite : Lot 2